Sprint carryover when the code is done but not accepted

Stefan-Iulian Tesoi · · 6 min read

Two worn vintage suitcases, one brown leather and one black with red trim, standing in the corrugated metal hold of a luggage van. Packed and ready, and still waiting to be carried on.

Because the code was never the slow part. Sprint carryover on a team running coding agents is mostly items waiting for code review, items blocked on a question nobody answered, and items rejected late against an acceptance criterion. Sort the carried items by those three causes before the next planning, because each one needs a different fix.

On a human team, carryover usually meant an estimate was wrong: a story took eight days instead of three, and the sprint ended with it half built. A coding agent finishes a well-specified item in under an hour, so that explanation has mostly gone. The board still shows unfinished stories at sprint end, and the column each one sits in says why.

What causes sprint carryover once agents write the code?

Work that waits, rather than work that is unbuilt. An item still open on the last day of a sprint has usually been built already, and is held up by something only a person can supply: a review, an answer or a corrected criterion.

The arithmetic is simple and unforgiving. Two agents can hand in thirty items in a five-day sprint, six a day. A reviewer who clears four a day falls two behind every day, and on Friday evening ten items are built, green and carried into next week. None of the code was late.

The same week would have looked healthy on a human team. Planning was built around execution as the constraint, which sprint planning with AI agents no longer can assume, and the constraint has moved to the people at both ends of the work.

Waiting for review, blocked, or rejected late?

Those are the three causes, and the column an item ends in usually tells them apart. Teams call it sprint spillover, carryover or rollover; the cause matters far more than the name.

CauseWhere it sits at sprint endWhat it signalsThe fix
Waiting for reviewIn Review, evidence attachedReview capacity is below the hand-in rateReview every day, and cap the queue
Blocked on a questionReady, with a blocker raisedThe item was planned before it was specifiedAnswer it before planning, or take it out of Ready
Rejected lateBack in Ready after a reviewA criterion was wrong, missing or changedFix the criterion, not only the code

An item waiting for review is the cheapest carryover to clear, because the work exists. A blocked item is often waiting on another item, which is a sequencing problem planning should have caught. A late rejection is the expensive one: the agent's run, the review and the rework all repeat, and they repeat again next sprint if the criterion stays wrong. Rejected agent work is more often a specification defect than a coding one.

Should a carried item keep its place in the next sprint?

Only if it is still among the most important work and its cause has been dealt with. Carrying an item forward automatically treats last week's priority as this week's, and repeats whatever stopped it.

The 2020 Scrum Guide is plain about incomplete sprint items: work that does not meet the Definition of Done returns to the Product Backlog "for future consideration". That is a re-ranking, not a reserved first slot.

In practice the three causes get different answers:

Laimonade carries unfinished items forward when a sprint closes on Monday, and each keeps its column, so an item In Review stays In Review rather than starting over. The sprint workflow also subtracts carried-in points from the new week's velocity, so finishing last week's work does not flatter this one.

Fixing each cause before the next planning

Each cause has a fix that belongs in the week, not in the retrospective.

  1. Move review into the day. At ten to twenty minutes an item, ten carried items are two to three hours of review. Do them before planning, then set a limit: when more than a day's worth of items wait In Review, the agents stop taking new work.
  2. Give every blocker an owner and a date. A question raised on Tuesday and answered the following Monday has cost a week. If it cannot be answered before planning, the item leaves Ready.
  3. Write the rejection reason on the item. The reviewer names the criterion that failed and whether the code or the criterion was wrong. The second kind is fixed in the item before the agent runs again.
  4. Stop planning items that are not ready. An item without checkable acceptance criteria is the one most likely to be blocked or rejected late. Leave it out, however important it is.

Carryover used to measure how wrong the estimates were. Once agents build, it measures how long finished work waits for a person.

How do you track carryover so the trend is visible?

Count carried items in each sprint, split by cause, and watch the ratio rather than the total. The ratio is items carried divided by items planned. Ten carried out of thirty is a third of the sprint, and a third every week is a review problem rather than a bad week.

Two other numbers explain the ratio. Cycle time, from Ready to Done, shows how long an item takes end to end, and review wait, from In Review to Done, shows how much of that is waiting. When cycle time grows while build time stays under an hour, the growth is all waiting. Flow metrics on an agent team covers reading them together. Laimonade's management report shows carry-over ratio, cycle time and review wait for each sprint side by side.

Track the cause as well as the count. A spreadsheet column with three values is enough, and after four sprints it shows which fix to make first.

Frequently asked questions

Should carried items be re-estimated?

Only when the scope changed. An item waiting for review needs no new estimate, because the work is finished. A rejected item whose criterion was rewritten is effectively a new item and should be sized again. Re-estimating a carried item upwards to make the new sprint look fuller only hides the carryover it came from.

Is zero carryover a sensible target?

No. A team with zero sprint carryover is usually planning too little or closing the sprint early. Some carryover is normal when work arrives continuously: an item handed in on Friday afternoon carries over at no cost. The target is a stable, low ratio, with no item carried for a second week for the same reason.

Do partly finished items count towards the sprint?

No. An item counts when it is Done, accepted against its criteria, and not before. Partial credit for an item built but not reviewed hides exactly the review queue that causes carryover, and splitting points between sprints turns velocity into a negotiation. Report the item as carried, with its cause, and let the accepted total stand.